Icy winter, flooding prompt extra spending on I-74 bridge

I-74 Bridge at sunset taken from Isle of Capri. Photo by Mike Williams Davenport, IA

The Quad-City Times reports the Iowa Department of Transportation allocated the money to fund overtime needed to ensure the westbound bridge is finished in the first half of 2020. Danielle Alvarez, the Iowa agency’s project manager, says the $16 million will pay for additional labor and second-shift work.

Alvarez says a cold winter followed by flooding have made it unsafe to use extra-high cranes needed to install basket-handle style arches on the bridge connecting Iowa and Illinois.

Despite the extra cost, the bridge is expected to cost less than the budgeted $1.2 billion.