BETTENDORF, Iowa -- The Iowa and Illinois Departments of Transportation have released official plans for the I-74 detours as well as River Bridge construction updates.

If weather allows, detours will begin Monday, March 18.

All westbound I-74 traffic will detour to I-80 and I-280.

IDOT says the I-74 river crossing will be open throughout the construction. However, the Iowa bound bridge will be just one lane.

Beginning March 18, 2019

IDOT estimates the new Iowa bound bridge will be ready in the first half of 2020, but the schedule can change base on weather and flooding.

BEGINNING MARCH 20, 2019 THROUGH MAY 2019

Starting on March 18, local traffic to downtown Moline must use 19th street.

Local traffic to Bettendorf must use the Iowa bound I-74 on-ramp at River Drive.

All on and off ramps will stay open on the Illinois bound I-74 during 2019.

If everything goes according to schedule, beginning  March 20, local traffic on the Iowa bound bridge must take Exit 4 to Grant Street/U.S. 67 in Bettendorf.

From now until May 2019 local Bettendorf Trafic will be routed from Grant Street to 14th Street to Kimberly Road then to Middle Road to access Westbound I-74.

BEGINNING JUNE 2019

 

DETOUR: BEGINNING MARCH 18, 2019

Click here if you can't see the video.